In the case of Topalsson v Rolls-Royce the High Court dismissed the Claimants’ (Topalsson) claim that a services agreement had been unlawfully terminated and upheld the Defendants (Rolls-Royce) counterclaim for damages for repudiatory breach. This case highlights key issues that customers and suppliers should be considering when preparing and entering into agreements, including ensuring that key requirements and milestones are clearly recorded and that termination notices are validly served.
In October 2019, Rolls-Royce contracted with software developer Topalsson to develop a new digital visualisation tool allowing prospective customers to see photo-realistic renderings of Rolls-Royce cars with different custom configurations, before purchasing “the Agreement”.
Under the Agreement, Topalsson was obliged to meet milestone dates contained in an agreed implementation plan, which gave a detailed breakdown of the project programme “the December Plan”.
The software development and supply were delayed, and a revised plan with later delivery dates was agreed “the March Plan”.
Despite agreeing the revised March Plan, in April 2020 Rolls-Royce served a termination notice on Topalsson “the First Termination Notice” relying on Topalsson’s repudiatory breach for its failure to meet the December Plan dates. Topalsson rejected the First Termination Notice and affirmed the Agreement claiming that the milestones at issue had never been agreed.
Later in April 2022, Rolls-Royce served a further notice “the Second Termination Notice” purporting to terminate the Agreement for repudiatory breach for missing the March Plan deadlines or alternatively under clause 13.11 of the Agreement, which permitted termination if Topalsson failed to meet the agreed delivery or milestone dates.
Topalsson rejected the Second Termination Notice, alleging that Rolls-Royce was itself in repudiatory breach of the Agreement and purporting to accept that repudiatory breach to bring the Agreement to an end.
Topalsson issued proceedings against Rolls-Royce, claiming damages for unlawful termination and lost profits, alternatively for work carried out and/or invoices as at the termination date. Topalsson asserted that:
Rolls-Royce counterclaimed damages from the alleged repudiatory breach, claiming losses for software replacement costs, lost profits, and other related damages. Rolls-Royce argued that the December and March Plan dates were contractually binding.
The High Court (O’Farrell J) dismissed Topalsson’s claim that the Agreement had been unlawfully terminated and upheld Rolls-Royce’s counterclaim for damages for repudiatory breach.
The court found that the December Plan dates were contractually binding on Topalsson and Topalsson itself had proposed the December plan timeline to Rolls-Royce. Topalsson had agreed to the March Plan dates in circumstances where it had already failed to meet the December Plan. The court held that the milestone dates in these plans were contractually binding on the parties.
The court found that Rolls-Royce’s First Termination Notice was erroneous because it relied on Topalsson missing the December Plan dates, when the revised March Plan dates had already been agreed. This was, however, ultimately immaterial as Topalsson had affirmed the Agreement in response.
As to the Second Termination Notice, this was based on Topalsson’s failure to achieve the milestone dates set out in the March Plan and relied upon:
There was a key difference between the two termination avenues available to Rolls-Royce: case law is clear that the contractual termination right under clause 13.11 could only be exercised in respect of a significant or substantial breach justifying termination; whereas under clause 5.8, the parties had agreed that time for delivery deadlines was “of the essence“, i.e. a condition of the Agreement, any breach of which, irrespective of severity, would in principle amount to a repudiatory breach and justify termination.
On the facts, the court found that Rolls-Royce had been entitled to rely on either avenue as Topalsson’s delays were significant and “could not be described as a ‘near miss’. One milestone was achieved 11 days late and others were not achieved at all. The court found that under the Agreement, time was of the essence. That meant that timely performance was a condition of the Agreement and that any delay goes to the root of the contract, no matter how small or trivial the breach. Topalsson’s failure to meet the agreed milestones therefore amounted to a breach of condition in any case, which entitled Rolls-Royce to terminate either under the Agreement or at common law for repudiatory breach. The Second Termination Notice was accordingly valid.
Make sure milestones are clear:
Plan ahead:
Consider if time is of the essence:
Take care when drafting or receiving a termination notice:
This article was written by Nicole Simpson