Demand Connections Reform: A Curate Update – Data Centre Commitment Fees (DCCF) and Data Centre Queue Management Milestones
This website will offer limited functionality in this browser. We only support the recent versions of major browsers like Chrome, Firefox, Safari, and Edge.
Demand Connections Reform policy developments continue at pace.
Hot on the heels of the Connect Update published by Ofgem in June 2026 (please find a link to our article on this here), Ofgem published on 29 July 2026 a Curate Update (the Curate Update), together with draft amendments to: the Connection Use of System Code (the CUSC), the electricity distribution licence standard licence conditions and the Independent System Operator and Planner Licence (the ISOP Licence).
This article explores the significant proposals set out in the Curate Update in relation to:
The deadline for responses to the Curate Update consultation is 16 September 2026, with Ofgem stating that it intends to take decisions later in 2026.
BACKGROUND
There has been a huge increase over the past eighteen months in the number of electricity demand connection requests that the electricity distribution network operators (DNOs) and the National Energy System Operator (NESO) have received (and the MW being requested), with the majority of this being made up of new data centres.
The Curate Update (and before this the Call for Input on Demand Connections Reform (the Demand Call for Evidence)) indicates that between November 2024 and June 2025, total contracted offers in the electricity demand queue rose sharply from 41 GW (17 GW at transmission level, 24 GW at distribution level) to 125 GW (97 GW at transmission level, 28 GW at distribution level) in June 2025 (with the latest estimate that around 73 GW of the queue is comprised of proposed new data centre schemes). For comparison, the peak electricity demand in Great Britain on 11 February 2026 was 45 GW.
This has led to Ofgem, the Department for Energy Security and Net Zero (DESNZ), NESO and others grappling with the significant increase in the GB electricity connection queue and a lack of regulatory and commercial tools to remove non-viable projects (with a focus on data centres) from the queue.
Previous consultations, calls for input and responses on this topic include:
On 29 July 2026, Ofgem subsequently published the Curate Update which covers the work it is doing on the Curate pillar of demand connections reform, with the update setting out, among other things, further details on two proposals namely:
We explore these proposals below.
DATA CENTRE COMMITMENT FEE (DCCF)
The Curate Update sets out Ofgem’s current assessment that a lump-sum returnable commitment fee (Option 1A from the Demand Call for Evidence) is the best commitment fee design when assessed against Ofgem’s stated evaluation criteria of: (a) discouraging less-viable projects in the queue; (b) encouraging proactive self-termination; (c) encouraging timely progression; and (d) being simple to implement and administer.
Ofgem goes on to set out in detail its current thinking on the following points in relation to the DCCF:
Which GB data centre projects will be affected by the proposed Data Centre Commitment Fee (DCCF)?
Ofgem sets out in the Curate Update that it is proposing that a DCCF will, on implementation, apply to any unenergised GB data centre project (with data centre projects being defined by reference to “data centre service” and with this proposed to have the meaning given in the Cyber Security and Resilience (Network and Information Systems) Bill (although Ofgem notes that this definition may change)) that satisfies one of the following criteria:
Ofgem is also proposing currently that:
More widely, it is worth noting (among other things) that: (a) the Curate Update contains references to above 40 MW in places (rather than equal to or above), but the proposed CUSC amendments refer (in the definition of “DCCF MW Threshold”) to “at or above the MW capacity”; (b) the Curate Update generally contains references to the capacity of a data centre determining whether a fee may apply, but with it being unclear as to whether this means secured contractual import capacity in relation to a data centre or the computing capacity of the data centre (noting that a data centre could theoretically have a computing capacity of 100 MW, with 61 MW of “behind the meter” generation and 39 MW of secured import capacity). The proposed amendments to the CUSC (particularly the DCCF Data Centre definition) make it slightly clearer that Ofgem is likely to be focusing on the secured import capacity as the gating criteria to whether a fee applies, but the drafting is not as clear as it should be; and (c) the proposed terms “Demand Capacity” and “Embedded Demand Capacity” may cause confusion as we believe “Demand Capacity” may be defined in the BSC (not the CUSC), and with it being slightly unclear as to why Ofgem has selected this definition given the function of the “Demand Capacity” definition in the BSC.
What will the value of the Data Centre Commitment Fee (DCCF) be?
Ofgem has indicated that it is minded to adopt a policy of a flat £/MW fee (the “DCCF Value”) that will be multiplied by the import capacity in the accepted connection offer / bilateral connection agreement in respect of a DCCF Data Centre.
In relation to the £/MW fee itself, Ofgem is proposing a value in the range of £237,000/MW to £712,500/MW. By way of example, a yet-to-be-built Data Centre with a 100 MW of import capacity and a DCCF value of £237,000/MW would need to pay a DCCF of £23,700,000 (although please see below for interaction with wider grid securities).
Ofgem believes the £/MW fee (when multiplied by capacity) represents between 2.5% and 7.5% of its assessment of an average GB data centre project’s capital expenditure of £9,500,000 per MW (although Ofgem acknowledges that it has limited data on the capital expenditure in relation to smaller data centre projects). This value compares against benchmarks highlighted by respondents to the Demand Call for Evidence of €40,000 per MW based on the Spanish Government’s approach, $50,000 per MW figure from Texas, USA and an $70,000 per MW figure from Georgia, USA based on power reserved.
Ofgem is however seeking stakeholder feedback on a large number of the variables with regards the eventual £/MW fee, including what an average data centre project’s capital expenditure is, what impact different fees may have on a developer’s IRR in relation to a data centre and what the appropriate % of average capital expenditure should be.
The proposed CUSC and Independent System Operator and Planner Licence amendments also make clear that like the DCCF MW Threshold, NESO will have the right to, and may be required to (from time to time), adjust the DCCF Value (and potentially the way in which the value is calculated) on a periodic basis through the publication of an updated DCCF Statement.
When will the Data Centre Commitment Fee (DCCF) apply and when will the DCCF be kept by NESO?
Ofgem has proposed that the DCCF will apply to DCCF Data Centres from connection offer / bilateral connection agreement acceptance in respect of a DCCF Data Centre (or if later, from the time the policy is implemented) until energisation of that project.
Ofgem also sets out its current thinking that:
How will the Data Centre Commitment Fee (DCCF) interact with Cancellation Charges and Securities Requirements?
The proposed CUSC amendments indicate that Ofgem is proposing that the DCCF becomes a component of the wider “Cancellation Charge” in respect of a DCCF Data Centre and as a result is in addition to the normal components making up a Cancellation Charge (Section 15 of the CUSC sets out how a Cancellation Charge for any demand or generation project will be calculated).
Ofgem also acknowledges in the Curate Update that CMP417 (which looks to bring all demand projects into the User Commitment Methodology, aligning them with generation and storage projects) has been unanimously approved by the CUSC panel and that Ofgem has therefore conducted its assessments (with regards the Curate Update) on the assumption that the proposals in CMP417, or similar reforms, will be implemented.
The proposed amendments to Part 3 of Section 15 of the CUSC indicate in addition that the Cancellation Charge Secured Amount for a DCCF Data Centre (the value of the security that a developer needs to provide to NESO / a DNO to cover the potential value of the Cancellation Charge) will be calculated on the basis that the DCCF will be a separate variable that will always need to be fully secured; it will not be subject to the reducing % principles that apply to the other variables making up a Cancellation Charge Secured Amount as a generation project progresses. It is also proposed that the forms of security that can be provided for the DCCF will be the same as those acceptable to secure the Cancellation Charge Secured Amount, namely:
One point that the Curate Update doesn’t comment on though (and it will be interesting to see whether this is picked up in any of the consultation responses) is whether the general interest principles under the CUSC will also apply to any cash securities lodged with NESO to cover the DCCF (noting that in practice, it may be unlikely that too many developers will want to lodge a minimum of £9,480,000 with NESO) and whether any additional protections may need to be put in place taking into account the theoretical aggregate value of DCCF cash securities.
DATA CENTRE COMMITMENT FEE ANALYSIS
The Data Centre Commitment Fee proposals indicate Ofgem’s and DESNZ’s desire to reduce rapidly the number of data centre projects in the GB connection queue.
The proposals themselves broadly reflect principles that a section of the data centre market has been requesting for some time and will if implemented likely have the desired impact of incentivising developers of data centre projects (and potentially other projects) to leave the connection queue.
The proposed value of the £/MW fee will be one area that all stakeholders will likely have strong views on though, with others potentially commenting in addition on the fact that the proposed approach materially increases developers’ exposure to normal development risks (such as securing planning permission etc) and therefore creates too high a risk premium.
It is also clear that a number of details and concepts in relation to the Data Centre Commitment Fee need to be developed and refined further and we encourage all interested parties to respond to the consultation (the deadline for responses is 16 September 2026).
More widely, Ofgem, NESO and DESNZ have a tricky balancing act on their hands.
Most parties are agreed that a commitment fee is a sensible and effective way to remove “speculative” data centre projects from the queue (and incentivise new projects to not join the queue). Following the publication of the Curate Update though, a large number of stakeholders have expressed concern in relation to the proposed value of the commitment fee.
At a time when there is a global AI and digitalisation race, a high commitment fee will likely make Great Britain a less attractive place for investment in sorely needed infrastructure, also noting that GB energy costs, data sovereignty and copyright laws (as well as other matters) may mean that Great Britain is already not the first choice location for new data centre investment for certain parties.
Conversely, a low commitment fee may not have the desired impact of putting an end to “powered land banking” developments through either self-termination of agreements or the sale of the relevant project to an end developer.
Ofgem will also need to consider carefully the wider market impact of any commitment fee from the perspective of:
What is clear though is that the GB data centre development market is likely to undergo a period of profound and rapid change, with far reaching consequences.
DATA CENTRE PROJECT QUEUE MANAGEMENT MILESTONES
The Curate Update (and the proposed amendments to the CUSC) separately set out Ofgem’s proposals to vary grid connection offers and construction agreements to introduce new data centre specific queue management milestones (with Ofgem confirming that it is now not proposing to change the “Readiness” requirements under the Gate 2 Criteria Methodology for new data centre demand grid connection applications).
These new data centre milestones will sit alongside the existing NESO queue management milestones and the current Energy Networks Association milestones applicable to projects connecting to the distribution network.
The Curate Update goes on to set out the following proposals in relation to the proposed data centre specific milestones:
What new Data Centre Queue Management Milestones is Ofgem proposing?
Ofgem is proposing to introduce the queue management milestones set out in the table below (subject to certain exemptions and grace periods), with the way in which a milestone can be satisfied varying contingent on whether a developer selects one or both of the following pathways:
with a developer potentially having the option to switch between pathways once during the life of a project (the restriction on switching is designed to reduce the risk of gaming).
High level overview of proposed Data Centre Queue Management Milestones
| No. & Deadline | Milestone Overview | Evidential Requirements for Self-operation Pathway | Evidential Requirements for Lease or Sale Pathway |
M0.5.Dc 6 months post connection agreement signature | Pathway selection and non-binding compute offtaker evidence |
|
|
M2.Dc Same Deadline as M2 (Secured Statutory Consents) noting that this deadline will be contingent on how far out the contracted Completion Date is | Long-lead item procurement evidence | Evidence that a developer has entered into a genuine and material commitment to procure electrical equipment needed to connect and operate the data centre project. Options being consulted on include evidence of the procurement of transformers, switchgear, or other long-lead electrical equipment. Documentary evidence could include a purchase invoice, an executed procurement contract and/or a binding supplier commitment. | |
M6.Dc Same Deadline as M6 (Agree Construction Plan) noting that this deadline will be contingent on how far out the contracted Completion Date is | Financial capability evidence and technical capability evidence. | Financial Capability
| |
Technical Capability The relevant data centre has been assessed, designed or certified against a recognised data centre technical standard. This could include one of:
| |||
Customer Contract Not applicable | Customer Contract Binding compute offtaker evidence with options (which Ofgem is consulting on) potentially including:
| ||
Which GB data centre projects will the proposed new data centre milestones apply to?
The Curate Update sets out the options that Ofgem is considering currently in relation to a capacity threshold, whether the requirements should apply to both transmission and distribution connected projects, and how they should apply to existing and future projects.
Overall though, the Curate Update indicates that Ofgem’s preferred approach is that the new milestones will apply to projects:
Ofgem has, though, proposed potentially exempting certain projects, including: (a) data centres with existing agreements that meet the definition and are above a specific threshold, (if the DCCF is implemented), and/or if all queue management milestones up to M6 and beyond have been satisfied in respect of the project; and (b) data centres in the connection queue that are due to energise within six months of implementation of the additional data centre milestones. Ofgem has also proposed grace periods for certain projects.
Who will assess compliance with the milestone requirements and what will happen if a milestone is missed?
Ofgem has proposed that NESO and the electricity distribution network operators will (like the existing queue management process) be responsible for receiving, checking and recording readiness evidence, including how they assess whether evidence is valid, incomplete, expired, insufficient or no longer effective.
Ofgem has also proposed that:
DATA CENTRE QUEUE MANAGEMENT MILESTONE ANALYSIS
The introduction of new data centre queue management milestones for most data centre projects would appear to many to be a pragmatic way to ensure that developers of data centre projects (however well-funded) have clear incentives to develop their project(s) quickly, failing which the project can be removed from the demand connection queue.
As ever though, we suspect that the detail in relation to the actual milestones (and the evidence and timing requirements themselves) and how they will be implemented will be scrutinized heavily, with Ofgem likely to receive a large amount of feedback.
Four points that stand out to us initially though are:
Reflecting this, we recommend that all interested parties respond to the consultation by 16 September 2026 deadline, noting that Ofgem has said that it intends to take decisions later in 2026.
Burges Salmon has extensive experience advising clients on all aspects of the delivery of GB data centres, as well as on the numerous opportunities that are arising in the GB electricity network and energy sector more widely as a result of regulatory reforms and data centre developments.
If you would like to discuss how any of these potential reforms may affect you, please do get in touch with Alec Whiter.
This article was written by Alec Whiter.
Want more Burges Salmon content? Add us as a preferred source on Google to your favourites list for content and news you can trust.
Update your preferred sourcesBe sure to follow us on LinkedIn and stay up to date with all the latest from Burges Salmon.
Follow us