From grid risk to green light: structuring data centre investments in 2026
This website will offer limited functionality in this browser. We only support the recent versions of major browsers like Chrome, Firefox, Safari, and Edge.
However, the investment case is increasingly shaped by structural constraints: limited power availability, extended grid connection timelines, rising construction costs and heightened planning and regulatory risk. For investors, these factors are no longer peripheral development issues but core determinants of value, timing and exit.
As a result, capital is being committed earlier in the lifecycle, often ahead of secured power solutions or planning certainty, placing greater emphasis on risk allocation, funding flexibility and downside protection. Our experience advising investors and developers across data centre and energy transactions shows that successful investments are often underpinned by complex structuring from the outset, aligning on power strategy, governance and financing mechanics.
Rising data centre construction costs, uncertainty around power availability and increasing competition are combining to create significant challenges for investors and developers.
Escalating build costs, driven by materials, labour shortages and complex technical specifications for AI‑ready facilities, are placing pressure on project viability assumptions. At the same time, power sources are increasingly challenging to secure, with constrained grid capacity, extended connection lead times and evolving energy strategies introducing material timing and cost risks.
These challenges are intensified by fierce competition for viable sites, grid connections and capital, particularly where there are established or proposed UK data centre clusters. Investors and developers are therefore being forced to commit capital earlier in the development lifecycle, often before power solutions or planning outcomes are fully certain. As a consequence, traditional development models are more challenged, as developers must take earlier risks and may need to seek flexible funding structures to maintain stability.
Extended grid connection timelines and capacity constraints in certain areas are becoming key determinants of the success of a project. As reported in the JLL 2026 Global Data Center Outlook (2026 Global Data Center Outlook), the average grid connection lead time for a new 50 MW data centre in the UK is seven years. Power is no longer a technical workstream but a central investment risk that must be addressed at the outset.
These constraints mean that investors are increasingly looking to combine data centre assets with energy infrastructure, such as on-site generation, long‑term PPAs or co‑located renewables projects. Renewable energy generation and integrated battery storage systems offer some solutions, and there is increasing attention being given to the potential for nuclear power sources, such as small modular reactors, to provide long-term solutions.
The scale, power requirements and delivery risk of hyperscale and AI-ready data centres have created increasing challenges for developers who require access to capital managed by institutional investors, such as pension funds and specialist infrastructure funds, at an ever-earlier stage.
These constraints are driving a shift in how data centre investments are legally structured. Capital is being deployed earlier in the project lifecycle, often ahead of secured grid connections or final planning outcomes, requiring structures that can absorb prolonged uncertainty.
One key solution is the establishment of joint ventures between developers and institutional investors, allowing both parties to benefit from development expertise and long-term capital. We are well versed in supporting clients to put contracts in place that clearly apportion power, planning and cost overrun risks between parties and reflect parties’ rights and responsibilities in light of prolonged grid lead times and bespoke funding mechanics. We are also able to include extended long-stop dates, enhanced information rights and carefully calibrated exit and dilution provisions designed to reflect the current complexities of the grid connection landscape and parties’ evolving energy strategies.
In practice, developers are being required to lock in grid connection milestones and power procurement strategies far earlier than they might have previously envisaged, with transaction documentation increasingly sensitive to delay risks and termination scenarios. This shift is pulling financing discussions earlier, often before traditional construction or Notice to Proceed milestones are reached.
Investors must also factor in the potential application of the National Security and Investment Act 2021, which can introduce additional timing and conditionality risk for acquisitions involving specified data infrastructure activities, particularly where overseas capital is involved. Where applicable, this risk needs to be managed alongside financing and completion mechanics to avoid misalignment between regulatory clearance and funding availability.
Rising data centre construction costs, uncertainty around power availability and increasing competition are combining to create significant challenges for investors and developers.
Escalating build costs, driven by materials, labour shortages and complex technical specifications for AI‑ready facilities, are placing pressure on project viability assumptions. At the same time, power sources are increasingly challenging to secure, with constrained grid capacity, extended connection lead times and evolving energy strategies introducing material timing and cost risks.
These challenges are intensified by fierce competition for viable sites, grid connections and capital, particularly where there are established or proposed UK data centre clusters. Investors and developers are therefore being forced to commit capital earlier in the development lifecycle, often before power solutions or planning outcomes are fully certain. As a consequence, traditional development models are more challenged, as developers must take earlier risks and may need to seek flexible funding structures to maintain stability.
Extended grid connection timelines and capacity constraints in certain areas are becoming key determinants of the success of a project. As reported in the JLL 2026 Global Data Center Outlook (2026 Global Data Center Outlook), the average grid connection lead time for a new 50 MW data centre in the UK is seven years. Power is no longer a technical workstream but a central investment risk that must be addressed at the outset.
These constraints mean that investors are increasingly looking to combine data centre assets with energy infrastructure, such as on-site generation, long‑term PPAs or co‑located renewables projects. Renewable energy generation and integrated battery storage systems offer some solutions, and there is increasing attention being given to the potential for nuclear power sources, such as small modular reactors, to provide long-term solutions.
The scale, power requirements and delivery risk of hyperscale and AI-ready data centres have created increasing challenges for developers who require access to capital managed by institutional investors, such as pension funds and specialist infrastructure funds, at an ever-earlier stage.
These constraints are driving a shift in how data centre investments are legally structured. Capital is being deployed earlier in the project lifecycle, often ahead of secured grid connections or final planning outcomes, requiring structures that can absorb prolonged uncertainty.
One key solution is the establishment of joint ventures between developers and institutional investors, allowing both parties to benefit from development expertise and long-term capital. We are well versed in supporting clients to put contracts in place that clearly apportion power, planning and cost overrun risks between parties and reflect parties’ rights and responsibilities in light of prolonged grid lead times and bespoke funding mechanics. We are also able to include extended long-stop dates, enhanced information rights and carefully calibrated exit and dilution provisions designed to reflect the current complexities of the grid connection landscape and parties’ evolving energy strategies.
In practice, developers are being required to lock in grid connection milestones and power procurement strategies far earlier than they might have previously envisaged, with transaction documentation increasingly sensitive to delay risks and termination scenarios. This shift is pulling financing discussions earlier, often before traditional construction or Notice to Proceed milestones are reached.
Investors must also factor in the potential application of the National Security and Investment Act 2021, which can introduce additional timing and conditionality risk for acquisitions involving specified data infrastructure activities, particularly where overseas capital is involved. Where applicable, this risk needs to be managed alongside financing and completion mechanics to avoid misalignment between regulatory clearance and funding availability.
Power constraints and extended grid lead times are forcing investors to take a more creative approach to how UK data centre projects are structured, financed and delivered. Developers and investors can no longer treat power as a later technical issue; it must be secured and risk‑allocated at the outset. This is driving earlier engagement with institutional capital, lenders and energy providers, with transaction structures increasingly required to accommodate prolonged uncertainty on timing, cost and regulatory approvals.
In response, successful projects are adopting flexible joint venture and financing models that allow capital to be deployed ahead of traditional milestones. These can provide clear allocation of grid, construction and funding risks. Investors are also prioritising the combination of data centre transactions with energy infrastructure solutions, to protect the future value and enhance the bankability of their investment.
For both investors and developers, early legal input is essential to align power strategy, funding mechanics and exit flexibility, helping to ensure that projects remain bankable, resilient and commercially viable in a highly constrained market.

If you have any questions in relation to investment options and financing arrangements of data centres more widely, please do get in touch with Camilla Usher-Clark, Stuart McMillan or Briony Barber.
Explore the six key themes on our dedicated Data Centres hub, covering the critical power, planning, funding and delivery issues influencing data centre projects across their full lifecycle.
Find out moreWant more Burges Salmon content? Add us as a preferred source on Google to your favourites list for content and news you can trust.
Update your preferred sourcesBe sure to follow us on LinkedIn and stay up to date with all the latest from Burges Salmon.
Follow us